CSVT Section to Open to Traffic Earlier Than Scheduled

NORTHUMBERLAND – One section of the $900 million CSVT will be opening a little sooner than anticipated.

PennDOT officials announced during a virtual briefing Wednesday, the northern section of the CSVT project is now scheduled to open to traffic by late summer, weather permitting, “So that fourth and final contract for the northern section is well underway. We also completed a lot of the asphalt paving…that will be completed this spring. And then we will open the roadway to traffic…that will be late summertime.”

PennDOT’s Ted Deptula, says the work for that final contract now underway is constructing pavement on both ends of the river bridge.

He says PennDOT determined opening the northern section sooner will allow crews to finish work on one remaining portion of the project, ”We have to construct the southbound lanes between Route 405 and the existing four lanes…so the final construction of the northern section will be completed by late fall of 2022.”

And work on the southern section will also begin later this year. PennDOT’s Matt Beck says waterway and wetlands permits have been obtained and the department is 95% complete on obtaining right-of-way acquisitions.

“We anticipate the completing the few remaining claims over the next couple of months. When those right-of-way acquisitions are complete, we’ll advertise for construction bids for that first contract. Those bids will be opened early this year and we anticipate work under that contract starting this spring.”

Beck says the southern section is still expected to be open to traffic by 2027. The overall cost of the CSVT project has reached $900 million, but PennDOT says supply chain issues haven’t caused delays or extra costs.

 