|
Central Susquehanna Valley Roadwork
Click here for PennDOT's local Travelers Advisories and News
Releases
HUGHESVILLE -- A PennDOT
contractor will begin road work on Routes 118 and 405 in Hughesville
July 7. Work includes paving, placing concrete pipe and pavement
base drain to improve drainage, traffic signal upgrades at the
intersection with Main Street (Route 405), construction of concrete
curb and sidewalks, and placement of pavement markings and signs.
EXCHANGE -- PennDOT in
Montour County is scheduled to begin a bridge replacement project
along Route 44 in Anthony Township starting in early July.
The bridge carries Route 44 over McKee Run, about a mile west of
Exchange.
A detour is tentatively set to start on Monday, July 6. Work there
will be finished in August.
NORTHUMBERLAND COUNTY -- PennDOT has a bridge preservation contract
underway involving
the repainting of 10 state-owned bridges at various locations in
Northumberland County. There will be no restrictions to traffic.
The first structure is on
Schwaben Creek Road in Jackson Township just north of Red
Cross. The second structure will be
Lower Road in Little
Mahanoy Township over Zerbe Run. The third structure will be on
Route 890 in
Rockefeller Township over Shamokin Creek. The others will be done as
they get to them.
The remaining bridges are on
Route 54 north of Delaware Run in Delaware Township,
Route 901 south of
Ranshaw in Coal Township,
Brennan’s Farm Road in Mount Carmel Township,
Route 45 east of
Route 147 in East Chillisquaque Township,
Market Street over
Shamokin Creek in Snydertown Borough,
Upper Road south of
Trevorton in Zerbe Township and
Logan Run Road in
Rush Township.
NORTHUMBERLAND -- A PennDOT
contractor is still working Route 11 in Northumberland. The detour
is lifted, but work continues in that area, with resurfacing on the
Barry King Bridge and work at the underpass continuing. Expect
delays.
There will be an as yet
unscheduled one-weekend truck detour so the
intersection of Duke Street and Route 11 can be completed with
accelerated concrete. Trucks won't be allowed through this area
because of the restricted turning area. The entire project is
scheduled to be completed by July 31.
WHITE DEER -- A bridge
project is underway on the twin bridges carrying Route 15 over White Deer Creek
and White Deer Pike in White Deer Township, Union
County. Motorists encounter a cross over and single lane traffic in
each direction.
The project
will then shut down for the winter, and next year they will perform
the same work on the northbound structure. The work this year
will end by Thanksgiving. The total project completion date is
August 6, 2010.
DORNSIFE -- PennDOT is making drainage improvements (cross pipe replacements)
along Dornsife Mountain Road and a daylight detour
is posted. This project will
last into mid-July.
WATSONTOWN -- PennDOT
is tentatively scheduled to begin a bridge replacement project on
Hockley Hill Road in Lewis Township June 29. A
detour, using Route 54 and Warrior Run Boulevard, will be in effect.
Work will be complete in August.
SELINSGROVE -- A contractor has started a resurfacing project
along sections of Routes 35 and 522 in Snyder County. The
work will cover over nine miles of highway total, including a
section of Route 35 from Selinsgrove to Freeburg and a stretch of
Route 522 from Selinsgrove to Kreamer. There will be a 12’
vehicle-width restriction through the work zone on Route 35 from
June 15 through mid-August. The rest of the work will be finished in
October.
ORIENTAL -- A PennDOT contractor has closed Oriental Road and
implemented a detour for a bridge replacement project. The new
bridge is scheduled to be open to traffic by mid-October
SNYDER COUNTY - PennDOT is now doing bridge work
on Middle Creek Road in Spring Township. Middle Creek Road
is detoured just south of its intersection with Back Mountain
Road. This detour is scheduled to be in place through June 26.
NORTHUMBERLAND COUNTY
– PennDOT has started the rehabilitation of two state bridges:
+ The first bridge to
be replaced is on Short Road over Shamokin Creek in Shamokin
Township. The detour is now underway.
+ Following the first
bridge replacement, the contractor will move to the second bridge,
on Black Mill Road over Shamokin Creek, in Upper Augusta Township.
COLUMBIA COUNTY – An
update on the bridge replacement project on Route 254 in Greenwood
Township, Columbia County. Motorists are now using a temporary
roadway--with temporary traffic signals. This project is scheduled to be completed by July 31.
PAXINOS -- PennDOT is
rehabbing a bridge in Paxinos on Route 487. There are lane
restrictions and slight delays.
NORTHUMBERLAND COUNTY
– Crews have stared work on seven bridge decks, five of them on Route
147 between I-80 and the south end of Sunbury, one on Route 11 in
Northumberland Borough over the West Branch Susquehanna River, and
one on Route 61 in the city of Sunbury. Flaggers will control
traffic. This bridge work will be done by the end of July.
MILLVILLE -- Crews has
started a bridge project on Route 254, west of Millville in Columbia
County. Work is on the Route 254 Bridge over Spruce
Run, just southwest of the intersection with Spruce Run Road in
Madison Township. A detour is implemented using Eyers Grove
Road and Creek Road. Work is scheduled to be completed by July 6.
BLOOMSBURG -- Crews will
be setting concrete beams for the first phase of the new bridge on
Millville Road at the intersection with Route 42 near Buckhorn in
Columbia County. During this work, Millville Road traffic will be
reduced to a single lane, with traffic flow controlled by flag
people.
SELINSGROVE -- Crews are
working on the overpass bridge which carries Routes 11&15 southbound
onto the Selinsgrove Bypass in Snyder County. There is a new traffic
pattern on the bridge and the off-ramp beneath the bridge are
closed. This will continue until mid-July.
LAURELTON -- The Route
235 bridge over Laurel Run in Hartley Township, Union County, is
closed for safety reasons. A short detour is posted using Fairground
Road and Route 45. The detour adds about two miles and about
5-minutes to travels. The bridge is scheduled for replacement in
2013, but PennDOT is reassessing that timeframe.
CATAWISSA -- Road work
is underway on Route 487 between Catawissa and the Bloomsburg River
Bridge and Route 42 from Catawissa to Numidia. There will daytime
flagging and delays for motorists. Work will be done mid-July.
STILLWATER -- PennDOT is working on a bridge along Route 487 at
Stillwater in Columbia County. One lane is closed and a
temporary traffic signal is in use. Work will be done in
mid-July
BRIAR CREEK -- A bridge replacement project on Route 11 over Briar Creek,
just south of Berwick is underway. Two-way traffic will be
maintained throughout the project. The project is expected to be
completed by mid-September.
BUCKHORN -- A major road project is underway on eastbound Interstate
80 between Buckhorn (exit 236) and Lime Ridge (exit 241). The work
will include lane closures, the installation of concrete barriers
and ramp changes. Watch for changing traffic patterns and slow, or
stopped traffic. Some of this work will be complete
mid-summer. There are long delays during most daytime hours and
longer delays on Friday.
As
part of this project, a section of Creek Road in Hemlock Township
will be closed. A 20-minute signed detour is posted. Creek Road will
be closed during the summer and fall construction season.
|